The deal size and project completion deadline were not disclosed in the announcement, but people in the know have pegged the deal at over Rs 6,000 crore, reports Aneesh Phadnis.
The government-controlled City and Industrial Development Corporation (Cidco) has kicked off the tendering process for the over Rs 14,500 crore (Rs 145 billion) international airport project in neighbouring Navi Mumbai.
Maharashtra Chief Minister Ashok Chavan on Wednesday said he was hopeful of speedy clearance to the Navi Mumbai airport project but Environment Minister Jairam Ramesh feared it would destroy large swathe of mangroves at the proposed site.
After months of uncertainty, there is finally a glimmer of hope for the proposed Navi Mumbai airport. Environment & Forests Minister Jairam Ramesh told a TV channel today that he had already spoken to his counterpart in the aviation ministry, Praful Patel, and hoped "to find a compromise soon". "There will be an agreement. Our team is going to Navi Mumbai," Ramesh said.
Land acquisition issues & costs a big query; Cidco wants these fully addressed before calling preliminary bids.
British architecture firm Zaha Hadid Architects bagged the contract from Navi Mumbai International Airport Limited after a 12-week design competition, and will design the new airport's Terminal 1 and air traffic control tower.
Offers 12.60% in revenue share to Cidco, while only other bidder GMR offered 10.44%.
This is the question that comes again and again in the mind of every Mumbaiker regarding the Navi Mumbai airport. Though the proposal has been going back and forth to the Union Environment Ministry many-a-times, the ministry is yet to give a green signal to the project citing environmental concerns.
The last hurdle in the way of a second airport for Mumbai, at Navi Mumbai, was cleared by the central government on Monday. The Union ministry of environment and forests issued a notification granting exemption to the second airport from costal regulatory zone regulations, on the lines of an earlier exemption granted for an airport at Port Blair in the Andamans.
NMIAL is spending close to Rs 18,000 crore to get the airport up and running.
The airport, coming up in neighbouring Navi Mumbai, is expected to relieve the pressure on the Mumbai international airport. Some local politicians had demanded that the new airport be named for farmer leader late D B Patil. Urban Development Minister Eknath Shinde, who made the announcement, said the chief minister has assured the DB Patil Action Samiti, which is raising this demand, that some other project will be named after the farmer leader.
Tenders for the proposed Navi Mumbai airport are likely to be floated in the next six month and the project is 'very much on track', Civil Aviation Minister Praful Patel said on Monday.
After pleas for an early clearance to the long-pending Navi Mumbai airport project, Prime Minister Manmohan Singh on Friday said he would personally look into the issue to resolve the matter at the earliest.
IndiGo is undertaking a comprehensive review of its long-standing policy against fuel hedging, particularly in light of rising jet fuel prices and its ambitious long-haul expansion plans. CEO Willie Walsh stated that while domestic competitors don't hedge, international expansion necessitates a re-evaluation to manage risk and provide stability against volatile fuel costs.
IndiGo CEO Willie Walsh announced that the airline expects to begin receiving wide-body A350 aircraft from the second quarter of 2028, featuring a three-class configuration, as the airline sees significant opportunities in the long-haul market despite industry challenges like rising fuel costs.
Union ministry of home affairs changed its mind and gave bid clearance for Hiranandani Developers and its consortium partner, Zurich Airport
Under the hybrid-till model, a portion of non-aeronautical revenue (commercial revenue) at the airport is taken into consideration while fixing the landing and parking charges, user fees and other aeronautical charges.
CIDCO moves Supreme Court against Rs 1,200 cr compensation order for land parcel
Let's take a detailed look at why this project is yet to take off.
GVK Group that runs the swanky MIAL (Mumbai international airport) pipped rival GMR Group to bag the contract for the proposed facility in Navi Mumbai which will ease the severe congestion at the Chhatrapati Shivaji International Airport.
It is clear from the records that the land is in possession of CIDCO for several years.
Officials of the state urban development ministry confirmed the development to Business Standard on Monday after a meeting between Chavan, City and Industrial Development Corporation Vice-Chairman and Managing Director Sanjay Bhatia and other government officials.
The outer structure of Navi Mumbai International Airport's first terminal building is almost ready. Exactly behind the under-construction building, stands a partially demolished hill. Executives from the airport company are now hopeful the hill will be flattened by mid-January, paving the way for the first commercial take-off by December next year.
Reconstruction of the terminal is expected to be completed by September 2028.
Notwithstanding opposition from some villages to the Rs 14,500-crore (Rs 145 billion) Navi Mumbai airport, the implementing body, Cidco, has decided to go ahead with the project and would issue 'request for qualifications' on February 5.
It took 13 years to get environmental clearance for the greenfield international airport at Navi Mumbai.
The state-run City & Industrial Development Corporation (Cidco), nodal agency for the proposed Navi Mumbai international airport, has asked the New Delhi-based National Institute of Disaster Management (NIDM) to prepare a risk assessment and disaster management plan for the project.
Strangely, a few days after filing the charges, the CBI teams arrived in Hyderabad and Mumbai to raid GVK's offices and found incriminating evidence, a reversal of the normal course of events.
Modi stressed the need to enhance aviation infrastructure capacity to meet the rising demand for air travel.
Firms are still barred from holding board positions in the special purpose vehicle that will develop the airport.
An environment impact assessment study by the Indian Institute of Technology, Mumbai, for the proposed Navi Mumbai international airport, has categorically said there should not be any compromise on retaining the geomorphology of rivers, the aquatic life and mangroves in the airport zone.
The new greenfield airport at Navi Mumbai will come up at the proposed site and not be shifted elsewhere. Maharashtra Chief Minister Vilasrao Deshmukh has also written to the Civil Aviation Ministry for building the airport at the originally proposed site. There had been demands to shift the proposed Navi Mumbai airport to a new site due to environmental issues. The regulator would look into aspects like aeronautical charges, user development fee and passenger fee.
Officials from the City and Industrial Development Corporation (Cidco) on Thursday expressed fears that the proposed international airport at Navi Mumbai could become unviable due to cost escalation, following prolonged delays.
Will be operational by the time Mumbai airport reaches its saturation capacity of 40 million.
Actual construction on the Navi Mumbai international airport, which received the much-awaited environment clearances early this week, would begin in October next year as certain formalities remained to be done, said the City and Industrial Development Corporation (Cidco), a nodal agency for the project.
People affected by the Navi Mumbai international airport insist they be allotted developed land as compensation, not cash as the land acquisition Bill, recently cleared by Parliament
The airport, which will now be built to handle 20 million passengers, will likely start operations by mid-2020. However, rating agency CRISIL in its report in May-end had said operations are expected to start in 2023.
An Indigo flight from Navi Mumbai to Srinagar sustained damage after hitting a Visual Docking Guidance System pole while being parked at Srinagar airport. All passengers and crew were safe, and an inquiry has been initiated to determine the cause.
This is the second extension for the bids since June 18.
EAC told Cidco during a meeting that it would visit the site in the third week of October before finalising its report. Cidco had clarified its stand on 61 points relating to the proposed airport and reiterated that there was no alternative site.